Road Construction UPDATE: Winslow Road Reconstruction

Post Date:08/31/2016 9:14 AM
Beginning Thursday, September 1, 2016, the Contractor will begin Stage C of the project. This means Winslow Road will be closed to traffic from just north of the southern entrance of Hunters Creek Way to just north of Bellboy Drive. There are a few things yet to be completed within Stage D, but that section will be open to local traffic once Stage C is closed.

Stage C is expected to take approximately 6 weeks to complete, weather and utility dependent. Depending on the residence you need to access, you may need to go use County Home Road. 

Winslow Road Reconstruction: Stage C - Detour Plan.

For more information regarding the Winslow Road Reconstruction project, please visit our project page.

For general road construction information regarding lane closures and street closures in Marion, please reference the 2016 Road Construction Map.
Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer