Asphalt Resurfacing Project Schedule Updates

Post Date:05/06/2016 9:30 AM

The annual asphalt overlay project is moving along more quickly than anticipated. The updated schedule is as follows:

Mobilization #1:  ~5.2.16 – 5.13.16
8th Avenue from 25th Street to 30th Street
5th Avenue from 13th Street to 31st Street
15th Avenue from Maplecrest to Northview Drive

Please note: 
8th Avenue eastbound traffic will be maintained (traffic will be moved to north or south lane as needed to maintain one lane of traffic eastbound) and a detour will be placed for westbound traffic from 31st Street to 10th Avenue to 25th Street.

5th Avenue westbound traffic will be maintained (traffic will be moved to the north or south lane as needed to maintain one lane of traffic westbound) and a detour will be setup for eastbound from 13th Street to 7th Avenue to 31st Street.

Mobilization #2:   ~5.16.16 – 5.27.16
22nd Street from 8th Avenue to 10th Avenue and Southview Drive from Twixt Town Road to Ridge Drive
26th Street from 3rd Avenue to 5th Avenue
4th Avenue from 27th Street to 31st Street

Mobilization #3:  ~5.31.16 – 6.10.16
A Avenue from 15th Street to 22nd Street
5th Street from 29th Avenue to 300’ North
12th Avenue from Maplecrest to Northview Drive

Mobilization #4:  ~6.13.16 – 6.21.16
South 14th Street from A Avenue to G Avenue
50th Street from 8th Avenue to 10th Avenue

As with all construction projects, the schedule is weather dependent.

With the exception of 5th Avenue and 8th Avenue projects; there will not be direct access to the properties, except for emergencies. Most nights there will be local access available. Contractor LL Pelling will notify the property/business owners of the access restrictions.

If you have any questions about this project please contact the Engineering Department at 319-743-6340.

You can also view the closures/detours via the 2016 Construction Map.