Storm Sewer Project

Print
Press Enter to show all options, press Tab go to next option
CONTRACT:

Abode Construction - $179,244.00

PROJECT OVERVIEW:
The project, using Storm Water Utility funding, includes the construction of storm sewer and draintile, as well as effected sidewalks, drives and ramps on 27th Street between 1st Avenue and 2nd Avenue. 2018 Storm Sewer

PROGRESS UPDATES:

 Work began on September 4, 2018 and is to be completed within 25 working days.  The project is complete and on the December 6, 2018 City Council Meeting Agenda to be accepted by the City.

UPDATE:11.29.18