CONTRACT:
BWC Excavating, LC - $611,239.75

PROJECT OVERVIEW:Northview

The project, using Neighborhood Street Improvements funding, includes the reconstruction of Northview Drive from 11th Avenue to 17th Avenue along with removal and replacement of driveways, storm sewer, subdrain, water main, and other associated work.

Sealed bids were received by the City of Marion on February 13, 2018. City Council held a public hearing on February 22, 2018 and accepted the bids and awarded the project to the low bidder, BWC Excavating, LC. The low bid amount is $611,239.75, which is 99% of the engineer's estimate ($615,776.50). 

PROGRESS UPDATES:

Temporary seeding is complete, the project is suspended for the winter.

The Contractor has used 85.5 of the 65 working days and 99% of the contract is complete. Liquidated damages in the amount of $500 per day will be assessed for each calendar day in excess of this schedule.  

UPDATED:11.29.18