2018 Sidewalk Assessment Project

Print
Press Enter to show all options, press Tab go to next option

 

CONTRACT:
Curtis Contracting Corp: $81,043.83

PROJECT OVERVIEW:

This annual program provides for the construction of sidewalks in areas where no sidewalk currently exists.

Sidewalk AssessmentLocations are added to a comprehensive list, reviewed for need, and recommended to City Council by a committee. The 2018 Sidewalk Assessment Project will occur along the west side of 29th Street from 12th Avenue to 18th Avenue.


PROGRESS UPDATES:
Work began on August 6, 2018 and is to be completed within 30 working days.  The contractor has used 30 of their 30 working days; 99% of the contract is complete. Liquidated damages in the amount of $300.00 per working day will be assessed for work not completed within this time. The contractor is working on completing the punchlist items.

UPDATED:
11.29.2018